Construction Impact
Active roadwork affecting bike paths and their impact on cycling volume.
Total Affected
9
Distinct construction zones impacting a bike path
Bike Paths Blocked
0
Fully closed to cyclists - requires detour
Bike Paths Obstructed
9
Partially obstructed - reduced width or shared lane
Active Bike Path Blockages(9)
Each row is an active road-work zone impacting a bike path. Click a street name to open an in-app map preview.
| Street | Borough | Status | Reason | Duration | Nearest Counter | Volume Impact |
|---|---|---|---|---|---|---|
| Pierrefonds-Roxboro | Obstructed | Construction/rénovation avec excavation | Jan 22, 2026 → Feb 18, 2026 15-60 days | ~14,857 m | -0.6% vs before Likely stable Avg. before construction: 18 (28 days of data) Avg. during construction: 18 (22 days of data) | |
| Ville-Marie | Obstructed | Construction/rénovation avec excavation | Jan 22, 2026 → Feb 23, 2026 15-60 days | ~241 m | -15.1% vs before Likely decrease Avg. before construction: 80 (28 days of data) Avg. during construction: 68 (22 days of data) | |
| Anjou | Obstructed | Autre | Jan 10, 2026 → Mar 11, 2026 15-60 days | ~4,282 m | -36.9% vs before Likely decrease Avg. before construction: 23 (28 days of data) Avg. during construction: 15 (24 days of data) | |
| Le Sud-Ouest | Obstructed | Autre | Jan 11, 2026 → Feb 26, 2026 15-60 days | ~2,397 m | -1.9% vs before Likely stable Avg. before construction: 86 (28 days of data) Avg. during construction: 84 (33 days of data) | |
| Anjou | Obstructed | Autre | Jan 10, 2026 → Mar 11, 2026 15-60 days | ~4,282 m | -36.9% vs before Likely decrease Avg. before construction: 23 (28 days of data) Avg. during construction: 15 (24 days of data) | |
| Anjou | Obstructed | Autre | Jan 10, 2026 → Mar 11, 2026 15-60 days | ~4,282 m | -36.9% vs before Likely decrease Avg. before construction: 23 (28 days of data) Avg. during construction: 15 (24 days of data) | |
| Mercier-Hochelaga-Maisonneuve | Obstructed | S-2 Infrastructure souterraine mineure ou équipement hors-sol - Réseaux de gaz | Feb 5, 2026 → Feb 20, 2026 15-60 days | ~2,552 m | -17.2% vs before Likely decrease Avg. before construction: 17 (22 days of data) Avg. during construction: 14 (14 days of data) | |
| Le Plateau-Mont-Royal | Obstructed | Égouts et aqueducs - Excavation | Feb 15, 2026 → Mar 2, 2026 15-60 days | ~1,457 m | Insufficient data Avg. before construction: 1 (22 days of data) Avg. during construction: 1 (4 days of data) | |
| Le Plateau-Mont-Royal | Obstructed | Construction/rénovation sans excavation | Feb 1, 2026 → Feb 20, 2026 15-60 days | ~701 m | +122.2% vs before Likely increase Avg. before construction: 1 (22 days of data) Avg. during construction: 1 (18 days of data) |